January 28, 2010: Ordered Finishing Kit
February 23, 2010: Received Finishing Kit Shipping Date
April 23, 2010: Finish Kit Arrived
April 25, 2010: Finished Finish Kit Inventory
Wheels and Brakes
March 23, 2010: Installed Tires and Tubes
July 8, 2010: Installed Master Cylinder Fittings
October 1, 2010: Received More Hoses From Bonaco
Canopy Frame
July 23, 2010: Started Canopy Hinge
July 24, 2010: Worked on Canopy Hinge Blocks
July 25, 2010: Worked on Canopy Hinges and Latch
July 26, 2010: Finished Canopy Hinge Blocks
August 13, 2010: Started Canopy Frame
August 22, 2010: Worked on Canopy Frame
August 23, 2010: Fabricated Canopy Frame Wedges
August 25, 2010: Riveted Canopy Frame Sides
September 4, 2010: Modified Canopy Frame
September 8, 2010: Trimmed Canopy, Started Canopy Frame Reinforcement
September 9, 2010: Worked on Canopy Frame Reinforcement
September 11, 2010: More Work on Canopy Frame Reinforcement
September 12, 2010: Finished Drilling Canopy Frame, Started Strut Mounts
September 13, 2010: Drilled and Attached Forward Strut Mounts
September 15, 2010: Fabricated and Attached Aft Strut Mounts
September 16, 2010: Disassembled Canopy Frame
October 6, 2010: Worked on Canopy Frame
October 8, 2010: Trimmed Canopy Frame Skin Ears
October 9, 2010: Canopy Frame is Ready for Priming/Painting
October 10, 2010: Painted Canopy Frame Components
October 11, 2010: Started Assembling Canopy Frame
October 14, 2010: Started Riveting Canopy Frame
October 24, 2010: Finished Riveting Canopy Frame
Canopy
August 26, 2010: Started Cutting Canopy
August 28, 2010: Placed Canopy on the Fuselage
August 30, 2010: Marked Forward Canopy Cut
August 31, 2010: Cut Front of Canopy
September 1, 2010: Prepped for Big Cut
September 2, 2010: Made the Big Cut
September 3, 2010: Trimmed Forward Canopy
September 4, 2010: Modified Canopy Frame
September 6, 2010: Further Fitting of Canopy
September 8, 2010: Trimmed Canopy, Started Canopy Frame Reinforcement
October 7, 2010: Started Prepping Cabin Frame
October 25, 2010: Final Fitting of Canopy
October 28, 2010: Drilled Canopy Sides
November 6, 2010: Countersunk Canopy Screw Holes
November 7, 2010: Worked on Canopy, Rear Window, and Final Tail Skin
Rear Window
November 7, 2010: Worked on Canopy, Rear Window, and Final Tail Skin
November 13, 2010: Prepped Rear Window for Drilling
November 14, 2010: Drilled Rear Window and Riveted Aft Top Skin
January 30, 2011: Finished Cutting Rear Window